Civil Tech v Hua Rong: Security of Payment Act & Cross-Contract Set-Offs

Civil Tech Pte Ltd appealed against the decision to dismiss its application to set aside an adjudication determination under the Building and Construction Industry Security of Payment Act. The Court of Appeal dismissed the appeal, holding that a respondent to a payment claim may not withhold payment based on a claim or asserted set-off which does not arise from the contract on which the payment claim is based. The grounds of decision were delivered by Sundaresh Menon CJ.

1. Case Overview

1.1 Court

Court of Appeal of the Republic of Singapore

1.2 Outcome

Appeal Dismissed

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The Court of Appeal held that under the SOPA, a respondent to a payment claim may not withhold payment based on a claim from a separate contract.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Hua Rong Engineering Pte LtdRespondentCorporationAppeal DismissedWon
Civil Tech Pte LtdAppellantCorporationAppeal DismissedLost

3. Judges

Judge NameTitleDelivered Judgment
Sundaresh MenonChief JusticeYes
Tay Yong KwangJudge of AppealNo
Steven ChongJudge of AppealNo

4. Counsels

4. Facts

  1. Civil Tech was the main sub-contractor for two Land Transport Authority construction projects.
  2. Civil Tech engaged Hua Rong as its sub-contractor for labour on both the T211 and C933 projects via separate contracts.
  3. Hua Rong submitted a payment claim for work under the T211 Contract.
  4. Civil Tech issued a payment response claiming Hua Rong owed it a substantial sum due to fraudulent claims under the C933 Contract.
  5. Civil Tech sought to set-off the payment claim based on the alleged fraudulent claims under the C933 Contract.
  6. The adjudicator determined that the Act did not permit setting-off claims from another contract.
  7. Civil Tech applied to set aside the adjudication determination, arguing the adjudicator erred in refusing to consider the set-off.

5. Formal Citations

  1. Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd, Civil Appeal No 153 of 2017, [2018] SGCA 12

6. Timeline

DateEvent
Hua Rong submitted a payment claim to Civil Tech
Civil Tech issued a payment certificate/response
The adjudicator released his determination
Hua Rong applied for and obtained leave to enforce the Adjudication Determination
Civil Tech applied to court to set aside the Adjudication Determination
Hearing of Civil Tech’s application
Hearing of Civil Tech’s application
Judge dismissed the application
Court of Appeal heard the appeal
Court of Appeal issued grounds of decision

7. Legal Issues

  1. Set-off
    • Outcome: The Court of Appeal held that a respondent to a payment claim may not withhold payment based on a claim or asserted set-off which does not arise from the contract on which the payment claim is based.
    • Category: Substantive
  2. Interpretation of Statutes
    • Outcome: The court interpreted the Building and Construction Industry Security of Payment Act to determine whether cross-construction contract claims are valid withholding reasons.
    • Category: Procedural

8. Remedies Sought

  1. Setting aside of adjudication determination

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation
  • Arbitration

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
W Y Steel Construction Pte Ltd v Osko Pte LtdHigh CourtYes[2013] 3 SLR 380SingaporeCited for the purpose of the Act to provide the construction industry with a low-cost, efficient and quick process for the adjudication of payment disputes.
Hua Rong Engineering Pte Ltd v Civil Tech Pte LtdHigh CourtYes[2017] SGHC 179SingaporeThe Judge held that in an adjudication under the Act, a respondent to a payment claim may only rely on reasons for withholding payment arising out of the Payment Claim Contract.
Rong Shun Engineering & Construction Pte Ltd v CP Ong Construction Pte LtdHigh CourtYes[2017] 4 SLR 359SingaporeCited for the 'one payment claim, one contract' rule.
Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) LtdHouse of LordsYes[1974] AC 689England and WalesCited for the principle that a respondent to a payment claim was entitled to rely on its remedies at common law, including the right of set-off, to withhold payment unless such remedies had been clearly excluded by contract.
Kum Leng General Contractor v Hytech Builders Pte LtdHigh CourtYes[1996] 1 SLR(R) 310SingaporeCited as a case that followed Gilbert-Ash.
Hiap Tian Soon Construction Pte Ltd and another v Hola Development Pte Ltd and anotherHigh CourtYes[2003] 1 SLR(R) 667SingaporeCited as a case that followed Gilbert-Ash.
Dawnays Ltd v F G Minter Ltd and Trollope and Colls LtdCourt of AppealYes[1971] 1 WLR 1205England and WalesCited as a case overruled by Gilbert-Ash.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Security of Payment Act
  • Payment Claim
  • Payment Response
  • Adjudication Determination
  • Cross-Construction Contract Claim
  • Set-off
  • Construction Contract

15.2 Keywords

  • construction
  • payment
  • adjudication
  • security of payment act
  • set off

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Arbitration
  • Contract Law