Mansource Interior v CSG Group: Overpayment Dispute in Construction Subcontracts
In a suit before the High Court of Singapore, Mansource Interior Pte Ltd sued CSG Group Pte Ltd, seeking $904,530.53 for overpayment under two subcontracts for a Changi Business Park project. CSG Group counterclaimed for variations. Justice Vinodh Coomaraswamy ruled in favor of Mansource Interior, finding that they had overpaid CSG Group and dismissing CSG Group's counterclaim in its entirety. The court determined that the subcontracts were re-measurement contracts and that Mansource Interior's re-measurements were accurate.
1. Case Overview
1.1 Court
High Court of the Republic of Singapore1.2 Outcome
Judgment for Plaintiff
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
The High Court found Mansource Interior overpaid CSG Group under two subcontracts and dismissed CSG Group's counterclaim for variations.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Mansource Interior Pte Ltd | Plaintiff, Defendant in Counterclaim | Corporation | Judgment for Plaintiff | Won | |
CSG Group Pte Ltd | Defendant, Plaintiff in Counterclaim | Corporation | Counterclaim Dismissed | Lost | A Rajandran of A Rajandran |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Vinodh Coomaraswamy | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Edwin Lee | Eldan Law LLP |
Poonaam Bai | Eldan Law LLP |
Charles Tay | Eldan Law LLP |
A Rajandran | A Rajandran |
4. Facts
- Mansource Interior was awarded a subcontract by Shimizu Corporation for interior fitting out works at Changi Business Park.
- Mansource Interior subcontracted wall finishes and joinery work to CSG Group via two re-measurement subcontracts.
- The wall finishes subcontract was valued at $1,252,750, and the joinery subcontract at $1,550,000.
- CSG Group served payment claims on Mansource Interior for both subcontracts in August 2013.
- CSG Group obtained adjudication determinations in its favor for both subcontracts in September 2013.
- Mansource Interior commenced an action claiming overpayment to CSG Group under both subcontracts.
- The subcontracts contained a clause requiring main contractor approval for variation works.
5. Formal Citations
- Mansource Interior Pte Ltd v CSG Group Pte Ltd, Suit No 1155 of 2013, [2017] SGHC 41
6. Timeline
Date | Event |
---|---|
Shimizu Corporation Pte Ltd awarded Mansource Interior Pte Ltd the subcontract for interior fitting out works for a section of the Changi Business Park project. | |
Mansource Interior Pte Ltd subcontracted the wall finishes work and the joinery work for the same section of the project to CSG Group Pte Ltd. | |
CSG Group Pte Ltd served on Mansource Interior Pte Ltd a payment claim under the wall finishes subcontract for the sum of $322,536.65. | |
CSG Group Pte Ltd served on Mansource Interior Pte Ltd a payment claim under the joinery subcontract for the sum of $324,812.68. | |
Mansource Interior Pte Ltd certified the sum of $93,732.10 for the wall finishes subcontract. | |
CSG Group Pte Ltd made an adjudication application under the Building and Construction Industry Security of Payment Act for the sum of $228,804.55 said to be due under the wall finishes contract. | |
CSG Group Pte Ltd made an adjudication application under the Building and Construction Industry Security of Payment Act for the sum of $268,544.78 said to be due under the joinery subcontract. | |
CSG Group Pte Ltd obtained an adjudication determination in its favour in the sum of $223,956.50 for wall finishes work. | |
CSG Group Pte Ltd obtained an adjudication determination in its favour in the sum of $296,719.58 for joinery work. | |
Mansource Interior Pte Ltd commenced action claiming that the final account between the parties showed that the plaintiff had paid the defendant under each subcontract more than the defendant was contractually entitled to. | |
Trial began | |
Trial | |
Trial | |
Trial | |
Trial | |
Trial | |
Trial | |
Judgment issued |
7. Legal Issues
- Overpayment Under Subcontracts
- Outcome: The court found that Mansource Interior had overpaid CSG Group under both subcontracts.
- Category: Substantive
- Breach of Contract
- Outcome: The court found that CSG Group was in breach of contract.
- Category: Substantive
- Estoppel by Convention
- Outcome: The court found that Mansource Interior was not estopped from relying on the re-measurement clause in the wall finishes subcontract.
- Category: Substantive
- Variation Claims
- Outcome: The court dismissed CSG Group's counterclaim for variation works, finding that the main contractor did not authorize or approve the variations.
- Category: Substantive
- Pay When Paid Provisions
- Outcome: The court held that Section 9 of the Building and Construction Industry Security of Payment Act did not render void any of the contractual provisions on which the plaintiff relies.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Overpayment
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
China Construction (South Pacific) Development Co Pte Ltd v Spandeck Engineering (S) Pte Ltd | High Court | Yes | [2005] SGHC 86 | Singapore | Cited regarding the interpretation of a contract based on the course of dealing between parties. |
Amalgamated Investment & Property Co Ltd v Texas Commerce International Bank Ltd | N/A | Yes | [1982] QB 84 | N/A | Cited regarding the interpretation of a contract based on the course of dealing between parties. |
MAE Engineering Ltd v Fire-Stop Marketing Services Pte Ltd | Court of Appeal | Yes | [2005] 1 SLR(R) 379 | Singapore | Cited for the requirements of estoppel by convention. |
LW Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd | N/A | Yes | [2011] 4 SLR 477 | Singapore | Cited regarding the nature of interim certificates in construction contracts. |
Rudhra Minerals Pte Ltd v MRI Trading Pte Ltd (formerly known as CWT Integrated Services Pte Ltd) | Court of Appeal | Yes | [2013] 4 SLR 1023 | Singapore | Cited regarding the principle that estoppel cannot be used as a cause of action. |
Sea-Land Service Inc v Cheong Fook Chee Vincent | Court of Appeal | Yes | [1994] 3 SLR(R) 250 | Singapore | Cited regarding the principle that promissory estoppel can only be used as a shield and not as a sword. |
Hi-Amp Engineering Pte Ltd v Technicdelta Electrical Engineering Pte Ltd | High Court | Yes | [2003] SGHC 316 | Singapore | Distinguished regarding the applicability of back-to-back clauses in subcontracts. |
GIB Automation Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd | N/A | Yes | [2007] 2 SLR(R) 918 | Singapore | Cited regarding the applicability of back-to-back clauses in subcontracts. |
Ong Seow Pheng and others v Lotus Development Corp and another | N/A | Yes | [1997] 2 SLR(R) 113 | Singapore | Cited regarding the principle that a court cannot award compensation on a cause of action that has not been pleaded. |
Maryani Sadeli v Arjun Permanand Samtani and another and other appeals | Court of Appeal | Yes | [2015] 1 SLR 496 | Singapore | Cited regarding the recovery of costs of previous legal proceedings as damages in subsequent proceedings. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
Building and Construction Industry Security of Payment Act, Section 9 | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Re-measurement contract
- Subcontract
- Variation works
- Adjudication determination
- Payment claim
- Back-to-back contract
- Interim certificate
- Final account
- Retention sum
- As-built drawings
15.2 Keywords
- Construction subcontract
- Overpayment
- Re-measurement contract
- Variation claim
- Building and Construction Industry Security of Payment Act
- Singapore High Court
17. Areas of Law
16. Subjects
- Construction Dispute
- Contract Law
- Building and Construction Industry Security of Payment Act