Jurong Readymix Concrete v Crescendas: Defective Concrete & Premature Formwork Removal Dispute
In a suit before the High Court of Singapore on 7 April 2005, Jurong Readymix Concrete Pte Ltd sued Crescendas Pte Ltd for $247,856.34 for ready-mix concrete supplied. Crescendas counterclaimed, alleging breach of contract and negligence due to the supply of slow-setting concrete, leading to demolition and reconstruction of columns, and sought $352,475.41 in damages. The court found in favor of Jurong Readymix on its claim and granted interlocutory judgment for Crescendas on the counterclaim, with damages to be assessed, subject to qualifications regarding the cause of the column defects and the reasonableness of Crescendas' actions.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for the plaintiff on its claim; interlocutory judgment for the defendant on the counterclaim with damages to be assessed, subject to qualifications.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment reserved
1.5 Jurisdiction
Singapore
1.6 Description
High Court case between Jurong Readymix Concrete and Crescendas concerning defective concrete supply and premature formwork removal, resulting in a counterclaim for damages.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Jurong Readymix Concrete Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff | Won | |
Crescendas Pte Ltd (formerly known as Tavica Design Pte Ltd) | Defendant | Corporation | Interlocutory Judgment for Defendant | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lai Siu Chiu | Judge | Yes |
4. Counsels
4. Facts
- Jurong Readymix Concrete supplied ready-mix Grade 40 concrete to Crescendas for a construction project.
- Crescendas discovered that test cubes from the concrete delivered on 12 and 13 July 2002 were still 'green' after 24 hours.
- Ng Kin Choy Gary from Jurong Readymix advised Crescendas to allow more time for the concrete to harden before removing formwork.
- Crescendas removed formwork prematurely, leading to chunks of concrete falling off columns.
- Tan Meng Liang, a project engineer, expressed concerns about hidden cracks and loss of compaction in the columns.
- Core samples revealed cracks in some columns, leading to a decision to demolish and reconstruct them.
- The demolition and reconstruction of the columns caused a delay in the project's completion.
5. Formal Citations
- Jurong Readymix Concrete Pte Ltd v Crescendas Pte Ltd (formerly known as Tavica Design Pte Ltd), Suit 18/2004, [2005] SGHC 67
6. Timeline
Date | Event |
---|---|
Letter of award issued for the project | |
Project commencement date | |
Original project completion date | |
Purchase order issued for concrete supply | |
Construction work commenced | |
Plaintiff delivered ready-mix concrete to the site | |
Plaintiff delivered ready-mix concrete to the site | |
Defendant discovered test cubes were still 'green' | |
Defendant allowed formwork removal | |
Defendant approved removal of formwork for columns cast with concrete from the batch of 13 July 2002 | |
Formwork for columns 1/E and 2/E were removed | |
Consultants expressed concerns about the failure of columns to set properly | |
Plaintiff took core samples from column 5/B and discovered cracks | |
Approval given for coring tests | |
Plaintiff recommended column 5/B be demolished | |
Defendant replied to plaintiff’s request | |
Site meeting regarding tests for core samples | |
Column 2/E ordered to be demolished and reconstructed | |
Inspection of remaining 12 core samples | |
Defendant informed plaintiff it would demolish five columns | |
Plaintiff informed defendant it would be more expedient to demolish the last seven columns immediately | |
Defendant requested plaintiff to return the core samples | |
Plaintiff claimed defendant had orally agreed to pay for demolition and reconstruction of the last seven columns | |
Andrew informed the plaintiff that Fukang engaged AL Technologies to do coring tests for the last seven columns | |
Core samples showed cracks | |
Defendant denied plaintiff's claim | |
Plaintiff’s solicitors requested that the plaintiff’s expert be allowed to view the core samples taken by the defendant | |
Demolition of the last seven columns commenced | |
Defendant re-erected all 14 columns | |
Project completed | |
Plaintiff filed suit | |
Judgment reserved |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the plaintiff breached the contract by supplying concrete that did not meet the required standards, but the defendant's actions contributed to the damages.
- Category: Substantive
- Sub-Issues:
- Failure to supply concrete of good and merchantable quality
- Failure to meet consultant's requirements
- Defective Works
- Outcome: The court determined that the defective works were caused by a combination of the plaintiff's supply of defective concrete and the defendant's premature removal of formwork.
- Category: Substantive
- Sub-Issues:
- Defective concrete supply
- Premature removal of formwork
- Damages
- Outcome: The court applied the rule on remoteness of damages, finding the plaintiff liable for some costs but not for losses that could have been avoided by the defendant.
- Category: Substantive
- Sub-Issues:
- Remoteness of damages
- Causation
- Delay in Completion
- Outcome: The court found that the delay in completion was primarily due to the defendant's poor project planning, not solely the plaintiff's actions.
- Category: Substantive
- Sub-Issues:
- Disruption of construction sequence
- Liquidated damages
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Negligence
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Hadley v Baxendale | Court of Exchequer | Yes | (1854) 9 Exch 341 | England and Wales | Cited for the rule on remoteness of damages in contract law. |
Victoria Laundry (Windsor) Ltd v Newman Industries Ltd | English Court of Appeal | Yes | [1949] 2 KB 528 | England and Wales | Cited for interpreting and restating the rule on remoteness of damages. |
Koufos v C Czarnikow Ltd (The Heron II) | House of Lords | Yes | [1969] 1 AC 350 | United Kingdom | Cited for interpreting and restating the rule on remoteness of damages. |
13. Applicable Rules
Rule Name |
---|
Order 40 of the Rules of Court |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Ready-mix concrete
- Formwork
- Slow setting
- Test cubes
- Compressive strength
- Core samples
- Demolition
- Reconstruction
- Liquidated damages
- Grade 40 concrete
- Windsor probe test
- Novus actus interveniens
15.2 Keywords
- concrete
- formwork
- construction
- breach of contract
- negligence
- damages
- delay
- Singapore
- High Court
17. Areas of Law
Area Name | Relevance Score |
---|---|
Defective Works | 80 |
Construction Law | 75 |
Breach of Contract | 70 |
Delay in completion | 70 |
Contract Law | 65 |
Damages | 60 |
16. Subjects
- Construction Dispute
- Contract Law
- Negligence