Jurong Readymix Concrete v Crescendas: Defective Concrete & Premature Formwork Removal Dispute

In a suit before the High Court of Singapore on 7 April 2005, Jurong Readymix Concrete Pte Ltd sued Crescendas Pte Ltd for $247,856.34 for ready-mix concrete supplied. Crescendas counterclaimed, alleging breach of contract and negligence due to the supply of slow-setting concrete, leading to demolition and reconstruction of columns, and sought $352,475.41 in damages. The court found in favor of Jurong Readymix on its claim and granted interlocutory judgment for Crescendas on the counterclaim, with damages to be assessed, subject to qualifications regarding the cause of the column defects and the reasonableness of Crescendas' actions.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for the plaintiff on its claim; interlocutory judgment for the defendant on the counterclaim with damages to be assessed, subject to qualifications.

1.3 Case Type

Civil

1.4 Judgment Type

Judgment reserved

1.5 Jurisdiction

Singapore

1.6 Description

High Court case between Jurong Readymix Concrete and Crescendas concerning defective concrete supply and premature formwork removal, resulting in a counterclaim for damages.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Jurong Readymix Concrete Pte LtdPlaintiffCorporationJudgment for PlaintiffWon
Crescendas Pte Ltd (formerly known as Tavica Design Pte Ltd)DefendantCorporationInterlocutory Judgment for DefendantPartial

3. Judges

Judge NameTitleDelivered Judgment
Lai Siu ChiuJudgeYes

4. Counsels

4. Facts

  1. Jurong Readymix Concrete supplied ready-mix Grade 40 concrete to Crescendas for a construction project.
  2. Crescendas discovered that test cubes from the concrete delivered on 12 and 13 July 2002 were still 'green' after 24 hours.
  3. Ng Kin Choy Gary from Jurong Readymix advised Crescendas to allow more time for the concrete to harden before removing formwork.
  4. Crescendas removed formwork prematurely, leading to chunks of concrete falling off columns.
  5. Tan Meng Liang, a project engineer, expressed concerns about hidden cracks and loss of compaction in the columns.
  6. Core samples revealed cracks in some columns, leading to a decision to demolish and reconstruct them.
  7. The demolition and reconstruction of the columns caused a delay in the project's completion.

5. Formal Citations

  1. Jurong Readymix Concrete Pte Ltd v Crescendas Pte Ltd (formerly known as Tavica Design Pte Ltd), Suit 18/2004, [2005] SGHC 67

6. Timeline

DateEvent
Letter of award issued for the project
Project commencement date
Original project completion date
Purchase order issued for concrete supply
Construction work commenced
Plaintiff delivered ready-mix concrete to the site
Plaintiff delivered ready-mix concrete to the site
Defendant discovered test cubes were still 'green'
Defendant allowed formwork removal
Defendant approved removal of formwork for columns cast with concrete from the batch of 13 July 2002
Formwork for columns 1/E and 2/E were removed
Consultants expressed concerns about the failure of columns to set properly
Plaintiff took core samples from column 5/B and discovered cracks
Approval given for coring tests
Plaintiff recommended column 5/B be demolished
Defendant replied to plaintiff’s request
Site meeting regarding tests for core samples
Column 2/E ordered to be demolished and reconstructed
Inspection of remaining 12 core samples
Defendant informed plaintiff it would demolish five columns
Plaintiff informed defendant it would be more expedient to demolish the last seven columns immediately
Defendant requested plaintiff to return the core samples
Plaintiff claimed defendant had orally agreed to pay for demolition and reconstruction of the last seven columns
Andrew informed the plaintiff that Fukang engaged AL Technologies to do coring tests for the last seven columns
Core samples showed cracks
Defendant denied plaintiff's claim
Plaintiff’s solicitors requested that the plaintiff’s expert be allowed to view the core samples taken by the defendant
Demolition of the last seven columns commenced
Defendant re-erected all 14 columns
Project completed
Plaintiff filed suit
Judgment reserved

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that the plaintiff breached the contract by supplying concrete that did not meet the required standards, but the defendant's actions contributed to the damages.
    • Category: Substantive
    • Sub-Issues:
      • Failure to supply concrete of good and merchantable quality
      • Failure to meet consultant's requirements
  2. Defective Works
    • Outcome: The court determined that the defective works were caused by a combination of the plaintiff's supply of defective concrete and the defendant's premature removal of formwork.
    • Category: Substantive
    • Sub-Issues:
      • Defective concrete supply
      • Premature removal of formwork
  3. Damages
    • Outcome: The court applied the rule on remoteness of damages, finding the plaintiff liable for some costs but not for losses that could have been avoided by the defendant.
    • Category: Substantive
    • Sub-Issues:
      • Remoteness of damages
      • Causation
  4. Delay in Completion
    • Outcome: The court found that the delay in completion was primarily due to the defendant's poor project planning, not solely the plaintiff's actions.
    • Category: Substantive
    • Sub-Issues:
      • Disruption of construction sequence
      • Liquidated damages

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract
  • Negligence

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Hadley v BaxendaleCourt of ExchequerYes(1854) 9 Exch 341England and WalesCited for the rule on remoteness of damages in contract law.
Victoria Laundry (Windsor) Ltd v Newman Industries LtdEnglish Court of AppealYes[1949] 2 KB 528England and WalesCited for interpreting and restating the rule on remoteness of damages.
Koufos v C Czarnikow Ltd (The Heron II)House of LordsYes[1969] 1 AC 350United KingdomCited for interpreting and restating the rule on remoteness of damages.

13. Applicable Rules

Rule Name
Order 40 of the Rules of Court

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Ready-mix concrete
  • Formwork
  • Slow setting
  • Test cubes
  • Compressive strength
  • Core samples
  • Demolition
  • Reconstruction
  • Liquidated damages
  • Grade 40 concrete
  • Windsor probe test
  • Novus actus interveniens

15.2 Keywords

  • concrete
  • formwork
  • construction
  • breach of contract
  • negligence
  • damages
  • delay
  • Singapore
  • High Court

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Negligence